Tooheys Brewery Bright Beer Cellar
Scope of Triplenine Group’s Work
Lion Nathan contracted Triplenine Group to install all process and services equipment and piping associated with the new 18 vessel cellar project.
This included:
Installation of approximately 12,000 metres of tube and pipe
Running new product and services piping from the existing plant to the new cellar
Running bright beer lines from the new cellar to the bottling and canning halls
Installing new integrated manifolds for filling and CIP at each filler station
Client
Lion / Tooheys Brewery
Industry
Beverage
Location
Lidcombe, NSW, Australia
Cost
$3 million
Duration
7 months
Completion Date
2012
Workforce at peak of project
22

Key Features of this Project
Short timelines for project completion and a requirement to keep existing facilities operational
Close collaboration with other contractors including the building contractor, vessel delivery contractor and structural steel erector teams
Client
Lorem Ipsum
Industry
Lorem Ipsum
Location
Lorem Ipsum
Cost
Lorem Ipsum
Duration
Lorem Ipsum
Completion Date
Lorem Ipsum
Workforce at peak of project
Lorem Ipsum
bottom of page

.png)