Workforce – Total at peak of project – 38 personnel
Scope
TRIPLENINE was contracted by Manildra Group to provide fabrication, installation and commissioning support of all process and services systems based on design specifications
Systems include the following:
Unloading, unpacking and sorting of all equipment shipped from Italy/France, (Approximately 10 x 40’ shipping containers) required for the completion of the installation as detailed in the Piping and Instrumentation Diagrams.
Installation of all vessels, valves, instruments, pumps, heat exchangers and other misc equipment
Unloading, unpacking and sorting of piping shipped from Italy (approximately 10 x 40’ shipping containers).
Fabrication and installation of all company supplied pipework. Piping will arrive generally as described in the piping isometric drawings and will require some site measurement and completion of fabrication of spools. Piping to be completed to ASME standards and insulated to client specifications
Insulation of installed pipe work as called for by specification attached. Insulation was fully clad in 304 stainless steel.
Customer supplied piping
Piping was designed and fabricated overseas and shipped to site in 40ft shipping containers.
Piping was left "Green" and required site measuring and final fitup for installation
A dedicated fabrication area was established on site complete with office, storage area, concrete floor and security for the extensive fabrication required.
The site workshop was approx 500mt from the construction site, carefull planning was required to transport large spool to the site, the site was also located adjacent to the main road tanker site access
The new plant was located adjacent to the existing ethanol which presented a major risk due to the explosive environment, anything that could cause potential spark was prohibited from being used on the construction unless there were strict controls and monitoring in place to prevent potential sparking.
Triplenine work closely with the All Construction Engineering installation crew to install the piping simultaneously with the structural steel
For further information on this project contact Triplenine and one of our managers would be more than happy to help
Safety on our site is of utmost importance to us, ensuring everyone go home safely is our priority.
"The recent Beverage Grade Distillery is typical of their work. It was completed professionally, on time and to a very high standard." Kane Livingstone, Manildra Group engineering manager.