INDUSTRIAL BEVERAGE PROJECT
Beverage grade ethanol plant
MANILDRA GROUP, BOMADERRY NSW

Client - Manildra Group
Project – Beverage grade ethanol plant
Cost – $2.8 Million
Duration – 9 months, completed Mid 2018
Workforce – Total at peak of project – 38 personnel

Scope


TRIPLENINE was contracted by Manildra Group to provide fabrication, installation and commissioning support of all process and services systems based on design specifications
Systems include the following:
  • Unloading, unpacking and sorting of all equipment shipped from Italy/France, (Approximately 10 x 40’ shipping containers) required for the completion of the installation as detailed in the Piping and Instrumentation Diagrams.
  • Installation of all vessels, valves, instruments, pumps, heat exchangers and other misc equipment 
  • Unloading, unpacking and sorting of piping shipped from Italy (approximately 10 x 40’ shipping containers).
  • Fabrication and installation of all company supplied pipework. Piping will arrive generally as described in the piping isometric drawings and will require some site measurement and completion of fabrication of spools. Piping to be completed to ASME standards and insulated to client specifications
  • Insulation of installed pipe work as called for by specification attached. Insulation was fully clad in 304 stainless steel.

Construction challenges


The new plant was located adjacent to the existing ethanol which presented a major risk due to the explosive environment, anything that could cause potential spark was prohibited from being used on the construction unless there were strict  controls and monitoring in place to prevent potential sparking.
Triplenine work closely with the All Construction Engineering installation crew to install the piping simultaneously with the structural steel 


For further information on this project contact Triplenine and one of our managers would be more than happy to help
CONTACT US
  • Process piping installed

    Our expert team of tradesmen and riggers carefully assembled the equipment and piping

    Button
  • Leadership in Safety


    Safety on our site is of utmost importance to us, ensuring everyone go home safely is our priority.

    "The recent Beverage Grade Distillery is typical of their work. It was completed professionally, on time and to a very high standard." Kane Livingstone, Manildra Group engineering manager. 