ASAHI BEVERAGES - HUNTINGWOOD , NSW
CLIENT – ASAHI BEVERAGE & PACIFIC PROCESS
Project – Spring water processing plant & services piping
Cost - $2.1Mil
Duration – 8 months
Completed - Nov 2017
Workforce - Total at peak of project - 21 personnel
q
Scope
TRIPLENINE was contracted by Pacific process to provide detailed design, fabrication, installation and commissioning of all process services based on design works carried out by Pacific Process.
The mechanical installation for the spring water processing portion of the contract inclusive of the
following works;
- Tanker Unload.
- Spring Water Storage Silos and Manifolds.
- Carbon Filter.
- Micro Filter and UV Treatment
- Ozonation
- CIP Kitchen
- Services Pipe Work
Services project
TRIPLENINE was contracted by Asahi beverage to design, supply, installation and commissioning of process and services
systems and piping to the new processing plant and filling line
The mechanical installation for the spring water processing portion of the contract inclusive of the
following works;
- Pipe bridges
- Cooling tower water
- Reclaim
- Sodium Hydroxide
- High pressure compressed air (40Bar)
- Low pressure compressed air
- Steam and condensate
- Hygiene station
- Towns water
- Trade waste
- Storm water