Project – Spring water processing plant & services piping
Cost - $2.1Mil
Duration – 8 months
Completed - Nov 2017
Workforce - Total at peak of project - 21 personnel
q
Slide title
Write your caption here
Button
Slide title
Write your caption here
Button
Slide title
Write your caption here
Button
Scope
TRIPLENINE was contracted by Pacific process to provide detailed design, fabrication, installation and commissioning of all process services based on design works carried out by Pacific Process.
The mechanical installation for the spring water processing portion of the contract inclusive of the