top of page
LogoPlaceholder.webp

project

Manildra Group Beverage Grade Ethanol Plant

Scope of Triplenine Group’s Work
Manildra Group contracted us to provide fabrication, installation and commissioning support for a new beverage‑grade ethanol distillery. This was to be located next to their existing industrial grade ethanol and refine ethanol provided from that plant.


For this project we:


  • Unloaded, unpacked and sorted equipment shipped from Italy (10 x 40’ shipping containers), following the requirements of the Piping and Instrumentation Diagrams

  • Installed all vessels, valves, instruments, pumps, heat exchangers and other miscellaneous equipment

  • Fabricated and installed over 5km of stainless steel pipework. Piping was completed to ASME standards and insulated to client specifications, fully clad in 304 stainless steel. All piping underwent Non-Destructive Testing prior to installation.

  • Established an on-site fabrication workshop for work including final piping measurements and spooling

Client

Manildra Group

Industry

Agribusiness / Beverage

Location

Bomaderry, NSW

Cost

~$2.8 million

Duration

~9 months

Completion Date

2018

Workforce at peak of project

38
Key Features of this Project
  • High risk environment. This new plant was adjacent to the existing ethanol plant, so any sparking could have triggered an explosion. We limited on-site activities which could cause sparking to the bare minimum, and employed strict controls and monitoring for the work which could not be completed elsewhere.

  • Installation of 8 large columns for the ethanol distillation process, the largest being 42 metres long with a weight of 52 tonnes

  • Coordination with All Construction Engineering crew, who were commissioned to supply structural steel works, so that piping and structural steel were installed simultaneously

  • Transportation of large spools - the on-site workshop was 500 metres from the construction site and close to the main road tanker access for the existing plant. Avoiding disruption to current operations was vital.

Triplenine Group Service Capabilities Used in this Project

General Fabrication

Sheet metal fabrication

Tube & Pipe Spooling

Tanks and pressure vessels

Process Skid & Manifold Fabrication

Coded Welding

Chemical Cleaning & Passivation

Hydrostatic Testing

Plant Installation

Client

Lorem Ipsum

Industry

Lorem Ipsum

Location

Lorem Ipsum

Cost

Lorem Ipsum

Duration

Lorem Ipsum

Completion Date

Lorem Ipsum

Workforce at peak of project

Lorem Ipsum
bottom of page