project

Archie Rose Distillery

Client

Archie Rose Distilling Co.

Industry

Distillery / Beverage

Location

Botany / Banksmeadow, Sydney, NSW, Australia

Cost

$5 million+

Duration

18 months

Completion Date

Early 2020

Workforce at peak of project

58
Scope of Triplenine Group’s Work
We were thrilled when specialist Scotland-based distillery designers Allen Associates contacted us based on word-of-mouth referrals – and even more thrilled to work with Archie Rose, Australia’s most awarded distillery, on their new production facility.


We provided:


  • Detailed design and layout finalisation

  • Fabrication and installation of systems including:

  • Mash house

  • Fermentation vessels

  • Whisky and gin stills

  • Distillate

  • Spirit handling

  • Cask filling & disgorging

  • IBC station

  • Tanker bay

  • CIP set

  • Process water systems

  • Heating and cooling systems

  • Compressed air

  • Waste handling

Key Features of this Project

An innovative and creative approach to layout planning was essential to fit all plant requirements into the limited footprint of the site.

Custom designs to accommodate Archie Rose’s unique production processes, including:


  • 2 copper pot whisky stills with neck cooling jackets which allow the team to adjust the still for different malts

  • Copper pot and column hybrid vacuum stills which mean the team can ‘cold distil’ botanicals for gin, preventing damage to the flavour. Multiple configurations for each still mean different botanicals are distilled differently.


Advanced energy efficiency, reducing power, gas and water usage per litre of alcohol by 30% over the original Rosebery site.

Triplenine Group Service Capabilities Used in this Project

General Fabrication

Sheet metal fabrication

Tube & Pipe Spooling

Tanks and pressure vessels

Process Skid & Manifold Fabrication

Orbital Welding

Coded Welding

Chemical Cleaning & Passivation

Hydrostatic Testing

Non-destructive Testing

Plant and Engineering Design

Plant Installation

Client

Lorem Ipsum

Industry

Lorem Ipsum

Location

Lorem Ipsum

Cost

Lorem Ipsum

Duration

Lorem Ipsum

Completion Date

Lorem Ipsum

Workforce at peak of project

Lorem Ipsum
bottom of page