Manildra Gluten Dryer 8 Mechanical Installation
Scope of Triplenine Group’s Work
Triplenine Group was commissioned to manufacture and install piping for Manildra Group’s new state-of-the-art Gluten Dryer 8 facility in Bomaderry.
This included:
12 kilometres of stainless-steel tubing, fabricated to stringent food-grade hygienic standards. Our specialist welders ensured every joint met the highest quality requirements, with argon purging and careful polishing to maintain a flawless internal finish for optimal cleanability.
Offsite fabrication and pre-spooling of piping assemblies. Restricted site space and the unique design of the new building, which spans five levels and is separated into wet and dry process areas, made this the best solution.
Integrating complex piping networks, process tanks and support systems into a sophisticated food processing facility, with dedicated wet and dry areas, hygienic labour and precision process systems
We combined workshop precision, onsite expertise, and strong project coordination, to meet the demanding schedule and quality standards of this turnkey mechanical installation.
Client
Manildra Group
Industry
Agribusiness / Food
Location
Bomaderry, NSW, Australia
Cost
$8.52 million
Duration
14 months
Completion Date
May 2023
Workforce at peak of project
58

Key Features of this Project
By delivering prefabricated spools ready for installation, we reduced onsite welding, improved quality control, and kept installation on schedule.
Meticulous planning and collaboration between the builder, their contractors, our workshop and our site team meant equipment and piping installation was aligned with building progress. Installation was staged floor-by-floor, from the ground up, to minimise delays and control costs.