Manildra Group Starch Dryer
Scope of Triplenine Group’s Work
The Manildra Group contracted us to look after the fabrication and installation of new equipment piping to expand their starch drying capability at Bomaderry site. They planned to add a new 20 tonnes-per-hour starch dryer in a stand-alone new building, with wet product feed and various plant services supplied from their existing starch production facility.
Systems include the following:
RO (reverse osmosis) water supply
Primary wet starch supply from existing hydrocyclone feed tank
Secondary wet starch supply to/from existing reaction tanks 1 & 2
Clarified process effluent and process effluent
Waste water
Steam supply, steam condensate return, and compressed air supply
Client
Manildra Group
Industry
Agribusiness
Location
Bomaderry, NSW, Australia
Cost
$1.2 million
Duration
5 months
Completion Date
late 2016
Workforce at peak of project
22

Key Features of this Project
By pre-fabricating the pipe bridge, pipe support, manifolds and piping spools in our workshop, we met the desired completion date despite construction delays outside our area of scope.
Argon purging was required for all stainless steel tubing. QA activities – including our standard programs, a specific project Inspection and Testing Program, and third party inspections – found zero rejects.
Triplenine Group Service Capabilities Used in this Project
Client
Lorem Ipsum
Industry
Lorem Ipsum
Location
Lorem Ipsum
Cost
Lorem Ipsum
Duration
Lorem Ipsum
Completion Date
Lorem Ipsum
Workforce at peak of project

.png)