Tooheys Brewery Filtration Plant
Scope of Triplenine Group’s Work
Lion Nathan installed a new beer processing room in a two-stage project. GEA Australia contracted Triplenine Group to do the following work:
Stage One:
Installation of all new process piping external to the new processing room
Integration with existing piping
Stage Two:
Installation of service and process tubes and pipes for a brand new processing area
Client
Lion / Tooheys Brewery
Industry
Brewery / Beverage
Location
Lidcombe, NSW
Cost
$2.3 million
Duration
10 months
Completion Date
May 2009
Workforce at peak of project
28

Key Features of this Project
All integration work was performed outside production hours to avoid downtime. Critical cut-ins were carefully planned and executed.
In the new processing area, we installed 10km of services and process tube and piping.
Client
Lorem Ipsum
Industry
Lorem Ipsum
Location
Lorem Ipsum
Cost
Lorem Ipsum
Duration
Lorem Ipsum
Completion Date
Lorem Ipsum
Workforce at peak of project
Lorem Ipsum
bottom of page

.png)